Unit 6 awaits a Public Service Commission decision (docket U-37853). The Commission certified Unit 5 in August 2025. Its Unit 6 hearing was set for Oct. 29 to Nov. 2, 2026, and no ruling had been posted as of Nov. 5. This is the earlier phase of the Waterford 5 & 6 campaign; the air permit phase is on the main Waterford 5 & 6 page. Status as of 2026-11-05.

Meta Gets Cheap Power. You Pay the Bills.

$2+ billion gas plants to power Facebook's AI. Residents stuck with costs for 30+ years.

Corporate Welfare Disguised as Progress

The facts about who really benefits from these gas plants

Industrial Coalition Protests Entergy's Deal

"Entergy should not be allowed to use its monopoly structure to unreasonably impose financial risks on its existing captive ratepayers to serve the new data center load, while it reaps the return-on-equity benefits" — Louisiana Energy Users Group, including Exxon and Dow Chemical

Even major industrial corporations are protesting this arrangement that socializes costs while privatizing benefits.

Meta's AI data center in Richland Parish

Meta's Massive Energy Demand

Entergy rushed approval to meet Meta's timeline without competitive bidding

Louisiana LNG export tankers driving up gas prices

LNG Exports Drive Up Bills

"Higher natural gas prices in 2025 and 2026 are the result of strong export growth that persistently outpaces U.S. natural gas production" — U.S. Energy Information Administration

St. Charles Parish population declining since 2010

Population Decline Questions Growth Claims

If these projects create prosperity, why is population declining?

The Smoking Gun: Why Build Plants 200+ Miles Away?

Geographic Reality Exposes the Scam

Meta's data center is in Richland Parish (near Monroe). Waterford 5 & 6 will be in St. Charles Parish (near New Orleans) - over 200 miles apart.

If these plants are really "for" Meta's data center, why is Entergy building them hundreds of miles away when they're already building TWO gas plants right next to the data center in Richland Parish?

Map showing 200+ mile distance between Meta's AI data center in Richland Parish and Waterford 5 & 6 plants in St. Charles Parish

200+ Miles Apart: Technical Inefficiency Reveals True Purpose

Transmission Losses & Inefficiencies:

What This Really Reveals:

Key Fact from Entergy's Own Announcement:

"Build three combined-cycle combustion turbines with a combined capacity of 2,260 megawatts, two of which will be in Richland Parish" — Entergy Louisiana press release

If the purpose is serving Meta's data center, why build additional plants 200+ miles away when you're already building plants right next to the facility?

More Pollution in Cancer Alley

Adding fossil fuel infrastructure to already overburdened communities

Cancer Alley
3rd highest cancer rates in the nation
Environmental Racism
UN condemns disproportionate pollution burden
Gas Plant Failures
63% of capacity failed during Winter Storm Elliott
Killona Community
Historic area bears new pollution burden
Climate Impact
More fossil fuel dependence worsens storms
Water Usage
Massive cooling needs stress river systems

UN Human Rights Experts on Environmental Racism

"This form of environmental racism poses serious and disproportionate threats to the enjoyment of several human rights of its largely African American residents, including the right to equality and non-discrimination, the right to life, the right to health, right to an adequate standard of living and cultural rights"

— UN Human Rights Experts on Louisiana's Cancer Alley

St. Charles Parish communities already bear disproportionate pollution burdens. Adding more fossil fuel infrastructure perpetuates this documented pattern of environmental racism.

What Experts and Advocates Are Saying

Real concerns from regulators, scientists, and community leaders

"Any costs that Meta doesn't pay will go to the ratepayers. There's no doubt that the benefits are not accruing to the people who are bearing the costs."

Paul Arbaje, Union of Concerned Scientists

"I believe my most important job as a regulator is to trust but verify and the truth is, there were a lot of things that I just cannot verify at this moment. The fundamentals at the heart of this proposal were just too bitter for me to swallow."

Commissioner Davante Lewis, Louisiana PSC (Dissenting Vote)

"Our community is surrounded by industrial facilities sucking the life out of us daily with excessive cancer causing pollution. These pollutants have affected our health causing lung, prostate, liver, pancreas, and breast cancer."

Barbara Washington, Inclusive Louisiana

"We're dying from inhaling the industries' pollution. I feel like it's a death sentence. Like we are getting cremated, but not getting burnt."

Sharon Lavigne, Rise St. James, Goldman Prize Winner

"The push to force through approval of the Meta proposal is illustrative of our greatest concern – that corporate utilities believe the Louisiana Public Service Commission answers first and foremost to them, not Louisiana ratepayers."

Logan Atkinson Burke, Alliance for Affordable Energy

"Entergy can't keep the lights on on a good day."

Logan Wolfe, Earthworks

Attend the Open House Meetings

Ask tough questions. Demand transparency. Protect our community.

Wednesday, Sept 17

5:00-8:00 PM
River Parishes Community College
925 W Edenborne Pkwy, Boutte, LA

Wednesday, Sept 24

5:00-8:00 PM
Killona Fire Station
Closer to plant site

Top Questions to Ask Entergy Representatives:

  1. What percentage of Waterford 5 and 6 electricity will serve Meta versus St. Charles Parish residents?
  2. How much will residential electric bills increase when Meta's 15-year subsidy expires in 2041?
  3. Why didn't Entergy conduct a competitive bidding process as required by state law?
  4. What happens to ratepayers if Meta abandons the project early?
  5. How will these plants affect grid reliability during hurricanes when gas supply chains fail?
  6. Why choose gas over renewable energy plus storage, which now costs less?
  7. Given St. Charles Parish's declining population, how do you justify $2+ billion in new capacity?
  8. How much profit will Entergy shareholders earn annually from these plants?
  9. What are the health impacts of adding more fossil fuel infrastructure to Cancer Alley?
  10. Why not invest in energy efficiency that creates more local jobs at lower cost?

Bring your neighbors. Bring hard questions. Don't let them decide our community's future in secret.

Next phase: the LDEQ air permit (June 2026).

Tell a neighbor

The earlier phase of the Waterford 5 & 6 fight: who pays for gas plants built for Meta.

Share on Facebook Email it